[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904144":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904144,584,2,"多选题","投标工程量清单基本的编制流程包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计算基础标价",true,{"key":16,"text":17,"correct":18},"B","造价资料收集与调查",false,{"key":20,"text":21,"correct":14},"C","现场踏勘、询价",{"key":23,"text":24,"correct":14},"D","研究招标文件",{"key":26,"text":27,"correct":18},"E","选择报价策略调整标价，确定工程量清单报价","ACD","投标工程量清单是依据业主提供的招标工程量清单，计算各清单子目综合单价和合价后所形成的，为使得投标工程量清单更加合理。基本的编制流程包括：①研究招标文件；②现场踏勘、询价；③复核工程量；④计算基础标价；⑤选择报价策略调整标价，确定投标工程量清单报价。B项，造价资料收集与调查属于招标工程量清单基本的编制流程。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]