[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904141":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904141,584,2,"多选题","清单计价中的单价是综合单价，包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","安全生产费",false,{"key":16,"text":17,"correct":18},"B","缺陷修复",true,{"key":20,"text":21,"correct":18},"C","管理",{"key":23,"text":24,"correct":18},"D","保险",{"key":26,"text":27,"correct":18},"E","利润","BCDE","本题考查的是工程量清单计价。清单计价中的单价是综合单价包括为实施和完成合同工程所需的劳务、材料、机械、质检（自检）、安装、缺陷修复、管理、保险、税费、利润等费用，以及合同明示或暗示的所有责任、义务和一般风险，此单价直接与项目的计量、支付工作对应。而定额计价中的技术经济指标则没有这种内涵，常常用来复核、检验对应费用项目的计价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]