[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904140":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904140,584,2,"多选题","下列关于工程量清单分类说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投标工程量清单则由招标人确定",false,{"key":16,"text":17,"correct":18},"B","标底以编制的工程量清单预算为基础",true,{"key":20,"text":21,"correct":14},"C","结算工程量清单签订合同时确定的工程量清单",{"key":23,"text":24,"correct":18},"D","合同工程量清单是签订合同时确定的清单",{"key":26,"text":27,"correct":18},"E","招标工程量清单是在项目的招投标阶段编制","BDE","招标工程量清单是在项目的招投标阶段编制，通常由招标人提供。投标工程量清单则由投标人根据自身情况填报项目的单价、合计。招标工程量清单的标底或最高投标限价应以编制的工程量清单预算为基础确定。合同工程量清单是发、承包双方根据合同法、招（投）标文件及有关规定，以约定的工程量清单计价方式，签订工程承包合同时确定的工程量清单。结算工程量清单是在公路实施过程中或工程完工后，发、承包双方根据有关法律、法规，按合同约定用以计算确定的最终工程价款所确定的工程量清单。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]