[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904136":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904136,584,2,"多选题","下列项目中，不单独计量的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","箍筋",false,{"key":16,"text":17,"correct":18},"B","模板",true,{"key":20,"text":21,"correct":18},"C","脚手架",{"key":23,"text":24,"correct":18},"D","定位筋",{"key":26,"text":27,"correct":14},"E","预应力筋","BCD","本题考查的是工程量清单计量规则。除合同特殊约定单独计量之外，全部必需的模板、脚手架、装备、机具、螺栓、垫圈和钢制件等其他材料，应包括在工程量清单中所列的有关支付项目中，均不单独计量。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]