[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904119":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904119,584,2,"多选题","公路工程造价的编制原则包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","做好造价分析",true,{"key":16,"text":17,"correct":14},"B","贯彻国家技术政策",{"key":19,"text":20,"correct":21},"C","投资宽打窄用",false,{"key":23,"text":24,"correct":21},"D","接受“长官意志”指导",{"key":26,"text":27,"correct":14},"E","合理采用工程计价依据","ABE","公路工程造价的编制，应从建设项目的实际情况出发，遵循下列原则：①根据建设资金的筹资方式、项目的实施方法、施工单位的资质要求等，正确合理地采用工程计价依据。②严格遵守国家的方针、政策和有关制度，尤其是对工程造价管理的各项规定和要求。始终做到有依有据，讲求经济效益。克服“长官意志”的影响和干扰。③遵循价值规律的客观要求，从实际出发，采用先进合理的施工方法，既要把投资打足，也不要“宽打窄用”或有意扩大风险因素。④贯彻国家的技术政策、行业规定，做到技术先进、经济合理，从而合理确定工程造价，以维护建设各方的合法经济权益。⑤认真做好造价分析，有步骤、有目的地配合设计人员开展限额设计和优化设计。⑥应紧密与设计人员配合，相互信任、谅解，坚持实事求是的精神。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]