[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904065":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904065,584,2,"多选题","下列关于加劲梁施工的说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","钢桁架一般采用工地高强度螺栓连接施工",true,{"key":16,"text":17,"correct":14},"B","钢箱梁焊接前应先将待连接与已安装节段临时刚接",{"key":19,"text":20,"correct":21},"C","钢箱梁接头焊缝的施焊宜从桥面两侧向中轴线对称进行",false,{"key":23,"text":24,"correct":14},"D","接头焊缝形成并具有足够的强度和刚度后方可解除临时刚接",{"key":26,"text":27,"correct":14},"E","全铰接法桁架梁逐渐接近设计线形后，可对部分铰接点逐固结","ABDE","A项，加劲梁分为钢桁架、钢箱梁和预应力混凝土箱梁等形式，钢桁架一般采用工厂焊接、工地高强度螺栓连接施工。BCD三项，钢箱梁采用焊接连接时，应先将待连接钢箱加劲梁的节段与已安装节段临时刚性连接，接头焊缝的施焊宜从桥面中轴线向两侧对称进行。待接头焊缝形成并具有足够的强度和刚度后，方可解除临时刚性连接。E项，采用全铰接法架设时，在桁架梁逐渐接近设计线形后，可对部分铰接点逐固结。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]