[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904059":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904059,584,2,"多选题","下列关于大体积混凝土施工说法错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","配合比设计时宜提高水胶比",true,{"key":16,"text":17,"correct":14},"B","混凝土入模温度不应低于20℃",{"key":19,"text":20,"correct":21},"C","各层间浇筑间歇期控制在7天以内",false,{"key":23,"text":24,"correct":21},"D","分层浇筑时应对下层混凝土顶面作凿毛处理",{"key":26,"text":27,"correct":21},"E","混凝土内部通水降温时进出水口温差宜小于10℃","AB","大体积混凝土施工要求如下：①大体积混凝土配合比设计时宜降低水胶比、减少水泥用量，选用低水化热和凝结时间长的水泥品种，掺用可降低混凝土早期水化热的外加剂和掺合料。②大体积混凝土可分层、分块浇筑。分层浇筑时应对下层混凝土顶面作凿毛处理，且新浇混凝土与下层混凝土温差不宜大于20℃，并应采取措施将各层间浇筑间歇期控制在7天以内。③大体积混凝土浇筑宜在气温较低时进行，但入模温度不应低于5℃。大体积混凝土的温度控制宜按照“内降外保”的原则，对混凝土内部采取设置冷却水管通循环水冷却，对混凝土外部采取覆盖蓄热或蓄水保温等措施进行。在混凝土内部通水降温时，进出水口的温差宜小于10℃。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]