[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904052":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904052,584,2,"多选题","石灰稳定土底基层、基层的施工中做法正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工气温应不低于5℃，不宜安排在雨季施工",true,{"key":16,"text":17,"correct":14},"B","在铺筑上层前，应将下层的表面拉毛，并洒水湿润",{"key":19,"text":20,"correct":14},"C","施工机械不宜在已压成的底基层、基层上掉头",{"key":22,"text":23,"correct":14},"D","碾压完成后，必须保湿养护，可采用洒水、覆盖砂或低黏性土等",{"key":25,"text":26,"correct":27},"E","现场拌和过程中应及时检查含水率，使其等于或略小于最佳值",false,"ABCD","AB两项，石灰稳定土底基层、基层施工时，气温应不低于5℃，并在第一次重冰冻到来之前一个月完成，不宜安排在雨季施工；压实厚度，每层不小于100mm，也不超过200mm，并应先轻型后重型压路机碾压；在铺筑上层前，应将下层的表面拉毛，并洒水湿润。C项，施工机械不宜在已压成的底基层、基层上掉头。如必须在其上进行，应采取保护措施。D项，碾压完成后，必须保湿养护；养护期应不少于7天。养护方法可采用洒水、覆盖砂或低黏性土，或采用不透水薄膜和沥青膜等；养护期内除洒水车外不得通行车辆，采用覆盖措施的石灰稳定土层上，经批准通行的车辆应限制车速不得超过30km\u002Fh。E项，现场拌合过程中，应及时检查含水率，使其等于或略大于最佳值，同时使土和石灰充分拌和均匀，不得留有素土夹层。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]