[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904044":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904044,584,2,"多选题","下列关于配电工程塑料管敷设要求说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","塑料管直埋于现浇混凝土敷设时其温度不宜低于－15℃",false,{"key":16,"text":17,"correct":18},"B","塑料管应敷设在易受机械损伤的场所",true,{"key":20,"text":21,"correct":14},"C","管与盒（箱）应采用插入法涂专用胶合剂连接",{"key":23,"text":24,"correct":18},"D","暗配时与建筑物表面距离不应小于30mm",{"key":26,"text":27,"correct":14},"E","采用套管连接时。套管长度宜为管外径的1.5～3倍","BD","配电工程中塑料管敷设要求包括：①塑料管及其配件必须由阻燃处理的材料制成，不应敷设在高温和易受机械损伤的场所。②管口应平整、光滑，管与管、管与盒（箱）等器件应采用插入法涂专用胶合剂连接。当采用套管连接时。套管长度宜为管外径的1.5～3倍。③塑料管直埋于现浇混凝土内时，应采取防止发生机械损伤的措施，敷设时其温度不宜低于－15℃。④暗配时与建筑物、构筑物表面距离不应小于15mm。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]