[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904032":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904032,584,2,"多选题","下列关于光缆接续要求说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","接续前根据预留要求留足光缆长度",true,{"key":16,"text":17,"correct":14},"B","核对光纤、铜导线并编号作永久标记",{"key":19,"text":20,"correct":21},"C","纤盘的接头部位平直受力",false,{"key":23,"text":24,"correct":21},"D","增强保护可采用热可缩管法、套管法和W形槽法",{"key":26,"text":27,"correct":14},"E","接续完成后余纤盘在光纤盘片内，盘绕方向应一致","ABE","光缆接续的要求包括：①光缆接续前核对光缆程式、接头位置并根据预留要求留足光缆长度。②根据光缆的端别，核对光纤、铜导线并编号作永久标记。③光纤接续宜采用熔接法，接续完成并测试合格后立即做增强保护措施。增强保护可采用热可缩管法、套管法和V形槽法。④光纤全部接续完成后根据光缆接头套管（盒）的不同结构，将余纤盘在光纤盘片内，盘绕方向应一致。纤盘的曲率半径应符合设计要求，接头部位平直不受力。⑤光缆加强芯的连接应根据接头盒的结构夹紧、夹牢，并能承受与光缆同样的拉力，加强芯按悬浮处理。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]