[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904012":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904012,584,2,"多选题","下列关于地下连续墙施工说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","钢筋骨筋的接长宜采用绑扎连接",false,{"key":16,"text":17,"correct":14},"B","成槽方法仅有钻劈法、钻抓法、铣削法",{"key":19,"text":20,"correct":21},"C","槽段接头宜采用预埋钢筋钢板、设置剪力键等",true,{"key":23,"text":24,"correct":14},"D","单元槽段长度小于4m时，可采用2根导管灌注",{"key":26,"text":27,"correct":21},"E","单元槽段长度超过4m时，可采用2根导管灌注","CE","A项，钢筋骨筋的接长宜采用机械连接，骨架中间应留出上下贯通的导管位置。B项，地下连续墙的槽孔施工，可采用的成槽方法有钻劈法、钻抓法、抓取法、铣削法。地下连续墙分槽段（孔）施工，然后再由各墙段连接而成。C项，槽段接头一般采用预埋钢筋钢板、设置剪力键等连接方式。DE两项，水下混凝土应采用导管法灌注。单元槽段长度小于4m时，可采用1根导管灌注；单元槽段长度超过4m时，宜采用2或3根导管同时灌注。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]