[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904005,584,2,"多选题","下列关于后张法预应力施工说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预应力管道每个低点应设排水孔，最小内径为10mm",false,{"key":16,"text":17,"correct":14},"B","金属或塑料孔道横截面积不得少于预应力筋净截面积3倍",{"key":19,"text":20,"correct":21},"C","整体穿束时，束前端宜设置牵引头以保持预应力钢筋顺直",true,{"key":23,"text":24,"correct":21},"D","预应力钢筋张拉锚固后48h内未完成压浆的应采取防锈蚀措施",{"key":26,"text":27,"correct":14},"E","封锚采用与构件不等强度的混凝土并严格控制封锚后梁体长度","CD","A项，所有预应力管道均应在每个顶点设排气孔，需要时在每个低点设排水孔，最小内径为20mm。B项，采用金属或塑料管道构成后张预应力混凝土或构件的孔道时，管道内横截面积不得少于预应力筋净截面积的2倍。C项，整体穿束时，束的前端宜设置穿束网套或特制的牵引头，保持预应力钢筋顺直。DE两项，预应力钢筋张拉锚固后，孔道应尽早压浆，且应在48h内完成，否则应采取防止预应力钢筋锈蚀的措施。压浆完成后，需要封锚的锚具，应设置钢筋网浇筑封锚混凝土，封锚采用与构件同强度的混凝土并严格控制封锚后梁体长度。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]