[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903987":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903987,584,2,"多选题","下列关于顶推法施工说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","桥台后方设置预制场地",true,{"key":16,"text":17,"correct":18},"B","梁体整体浇筑，整体顶推",false,{"key":20,"text":21,"correct":18},"C","顶推法不适用于斜拉桥的施工",{"key":23,"text":24,"correct":14},"D","钢导梁长度为跨径的0.7倍左右",{"key":26,"text":27,"correct":14},"E","施工方法分为单点顶推和多点顶推","ADE","顶推法是指梁体在桥头逐段浇筑或拼装，用千斤顶纵向顶推，使梁体通过各墩顶的临时滑动支座面就位的施工方法。桥台后方设置预制构件施工场地，分节段浇筑梁体，并用纵向预应力钢筋将浇筑节段与已完成的梁体连成整体。顶推时在梁体前安装长度为顶推跨径0.7倍左右的钢导梁，然后通过水平千斤顶施力，将梁体向前方顶推出施工场地。顶推施工的方法可分为单点顶推和多点顶推，多应用于预应力钢筋混凝土等截面连续梁桥和斜拉桥梁的施工。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]