[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903952":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903952,584,2,"多选题","隧道洞口按设计要求应先施工完成，以减少干扰，并保证安全，下列关于洞口工程施工说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","端墙砌筑与墙背回填应两侧同时进行",true,{"key":16,"text":17,"correct":18},"B","洞门应尽可能安排在冬季或雨季施工",false,{"key":20,"text":21,"correct":18},"C","废弃的土石方应堆放在边坡、仰坡上方",{"key":23,"text":24,"correct":18},"D","边坡外的截水沟应于洞口土石方开挖后完成",{"key":26,"text":27,"correct":14},"E","洞口土石方在线位上进行仰坡自上而下的开挖","AE","A项，洞门端墙的砌筑（或浇筑）与墙背回填应两侧同时进行，防止对衬砌产生偏压。B项，洞门应及早修筑，并尽可能安排在冬季或雨季前施工。C项，进洞前必须完成应开挖的土石方，废弃的土石方应堆放在指定地点，不得在边坡、仰坡上方堆置废弃的土石方。D项，边坡、仰坡外的截水沟或排水沟应于洞口土石方开挖前完成。E项，洞口土石方在洞口施工放样的线位上进行边坡、仰坡自上而下的开挖。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]