[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903949":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903949,584,2,"多选题","小净距隧道施工中间岩柱的稳定与加固是整个小净距隧道施工的关键，VI～IV级围岩段可采用（ ）等预加固措施。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","超前小导管预注浆",true,{"key":16,"text":17,"correct":18},"B","管棚",false,{"key":20,"text":21,"correct":14},"C","水平贯通预应力锚杆",{"key":23,"text":24,"correct":18},"D","地表深层注浆",{"key":26,"text":27,"correct":14},"E","钢支撑","ACE","本题考查的是公路隧道施工技术。为确保小净距隧道施工的安全，必须采取措施对钻爆施工进行严格的监测和控制。为避免爆破震动波的叠加，必须采取微差控制爆破，后行隧道爆破震动速度应控制在150mm\u002Fs以内。中间岩柱的稳定与加固是整个小净距隧道施工的关键。VI～IV级围岩段可采用超前小导管预注浆、水平贯通预应力锚杆、钢支撑等预加固措施。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]