[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903944":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903944,584,2,"多选题","二次衬砌的应在初期支护变形基本稳定后进行，施作时间应满足的条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各测试项目所显示的位移率明显减缓并已基本稳定",true,{"key":16,"text":17,"correct":18},"B","防排水措施已全部施做完毕",false,{"key":20,"text":21,"correct":14},"C","已产生的各项位移已达预计位移量的80%～90%",{"key":23,"text":24,"correct":14},"D","周边位移速率小于0.1～0.2mm\u002F天",{"key":26,"text":27,"correct":14},"E","拱顶下沉速率小于0.07～0.15mm\u002F天","ACDE","本题考查的是公路隧道施工技术。二次衬砌的应在初期支护变形基本稳定后进行，施作时间应满足下列条件： （1）各测试项目所显示的位移率明显减缓并已基本稳定。 （2）已产生的各项位移已达预计位移量的80%～90%。 （3）周边位移速率小于0.1～0.2mm\u002F天，或拱顶下沉速率小于0.07～0.15mm\u002F天。 在满足上述条件后，应尽快进行二次衬砌的施作。自稳性很差的围岩，可能长时间达不到基本稳定条件，当初期支护的混凝土产生大量明显裂缝，而支护能力又难以加强、变形无收敛趋势时，应提前施作仰拱及二次衬砌。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]