[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903942,584,2,"多选题","下列符合湿陷性黄土路基施工规定的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","路床填料必须使用老黄土",false,{"key":16,"text":17,"correct":18},"B","浸水路堤不得用黄土填筑",true,{"key":20,"text":21,"correct":18},"C","路堑施工前，应做好堑顶地表排水导流工程",{"key":23,"text":24,"correct":18},"D","陷穴表面的防渗处理层厚度不宜小于300mm",{"key":26,"text":27,"correct":14},"E","挖方边坡顶以外倾向路基的陷穴应作适当处理，如串珠状陷穴","BCD","湿陷性黄土路基施工应符合以下规定：①黄土填筑路堤：路床填料不得使用老黄土。路堤填料不得含有粒径大于100mm的块料；在填筑横跨沟堑的路基土方时，应做好纵横向界面的处理；黄土路堤边坡应拍实，并应及时予以防护，防止路表水冲刷；浸水路堤不得用黄土填筑。②黄土路堑施工：路堑路床土质应符合设计要求，密实度不足时，应采取措施碾压至要求的压实度；路堑施工前，应做好堑顶地表排水导流工程。③黄土陷穴处理：路基范闱内的陷穴，应在其发源地点刘‘陷穴进口进行封填，并截排周围地表水；陷穴表面的防渗处理层厚度不宜小于300mm，并将流向陷穴的附近地面水引离；挖方边坡顶以外50m范围内、路堤坡脚以外20m范围内的黄土陷穴宜进行处理。挖方边坡顶以外的陷穴，若倾向路基，应作适当处理。对串珠状陷穴应彻底进行处治。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]