[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903932,584,2,"多选题","下列关于水泥混凝土路面施工的说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","振捣棒的持续时间不宜过振，也不宜少于60s",true,{"key":16,"text":17,"correct":18},"B","布料机与滑模摊铺机之间施工距离宜控制在5～10m",false,{"key":20,"text":21,"correct":18},"C","高速公路宜选用能一次摊铺2～3个车道宽度的滑模摊铺机",{"key":23,"text":24,"correct":14},"D","中、轻交通的混凝土路面上，横向缩缝可采用假缝加传力杆型",{"key":26,"text":27,"correct":14},"E","填缝料应与混凝土缝壁黏附紧密，其灌注深度宜为缝宽的1.5倍","ADE","A项，混凝土振捣时，振捣棒的持续时间应以拌和物全面振动液化、表面不再冒气泡和泛水泥浆为限，不宜过振，也不宜少于30s。B项，当坍落度在10～50mm时，滑模摊铺机布料松铺系数宜控制在1.08～1.15。布料机与滑模摊铺机之间施工距离宜控制在5～10m。C项，高速公路、一级公路施工，宜选配能一次摊铺2～3个车道宽度（7.5～12.5m）的滑模摊铺机。二级及二级以下公路路面的最小摊铺宽度不得小于单车道设计宽度。硬路肩的摊铺宜选配中、小型多功能滑模摊铺机。D项，在中、轻交通的混凝土路面上，横向缩缝可采用不设传力杆假缝型。在特重和重交通公路、收费广场、邻近胀缝或路面自由端的3条缩缝应采用假缝加传力杆型。E项，填缝料应与混凝土缝壁黏附紧密，其灌注深度宜为缝宽的2倍，当深度大于30mm时，可填人多孔柔性衬底材料。夏季应使填缝料灌至与板面齐平，冬季则应稍低于板面。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]