[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903931,584,2,"多选题","下列关于改性沥青混合料路面的说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改性沥青混合料储存时间不应超过48h",true,{"key":16,"text":17,"correct":18},"B","铺筑改性沥青及SMA路面时宜采用非接触式平衡梁",false,{"key":20,"text":21,"correct":14},"C","SMA混合料的拌和应严格控制拌和温度不得超过200℃",{"key":23,"text":24,"correct":18},"D","摊铺过程中出现异常且调节无效时，应立即停机查明原因",{"key":26,"text":27,"correct":14},"E","如果在指定温度内还未压实，为防止推移破坏，应改用钢轮碾碾压","ACE","A项，改性沥青混合料储存时间不应超过24h；回收的粉尘不得利用，应全部废弃在指定地点进行处理，防止污染环境。B项，铺筑改性沥青及SMA路面时宜采用非接触式平衡梁。C项，SMA混合料的拌和时间应适当延长，应严格控制拌和温度，不得超过195℃。D项，摊铺过程中应随时观察摊铺机的工作状态和摊铺层的外观质量，出现异常且调节无效时，应立即停机查明原因，进行调整。E项，改性沥青混合料的碾压较困难，应尽可能提高碾压温度和振动频率。如果在指定温度内还未压实，则应改用轮胎压路机碾压，不能用钢轮碾，更不能起振，防止推移破坏。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]