[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903930":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903930,584,2,"多选题","下列关于热拌沥青混合料路面的接缝处理说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","后摊铺部分完成留下20～30cm宽暂不碾压",false,{"key":16,"text":17,"correct":18},"B","半幅施工不能采用热接缝时，采用人工顺直刨缝或切缝",true,{"key":20,"text":21,"correct":14},"C","横接缝端部平整度不符合要求时，平行于路中线切齐清除",{"key":23,"text":24,"correct":18},"D","横向接缝的碾压先用双轮双振压路机进行横压，再改为纵向碾压",{"key":26,"text":27,"correct":18},"E","纵向冷接缝上、下层的缝错开15cm以上，横向接缝错开1m以上","BDE","热拌沥青混合料路面的接缝处理要求包括：①梯队作业采用热接缝，施工时将已铺混合料部分留下20～30cm宽暂不碾压，作为后摊铺部分的高程基准面。后摊铺部分完成立即骑缝碾压，以消除缝迹。②半幅施工不能采用热接缝时，采用人工顺直刨缝或切缝。铺另半幅前必须将边缘清扫干净，并涂洒少量黏层沥青。碾压时先在已压实路面行走，然后压实新铺部分，再伸过已压实路面10～15cm，充分将接缝压实紧密。③横接缝的处理时首先用3m直尺检查端部平整度。不符合要求时，垂直于路中线切齐清除。横向接缝的碾压先用双轮双振压路机进行横压，直至全部在新铺层上为止，再改为纵向碾压。④纵向冷接缝上、下层的缝错开15cm以上，横向接缝错开1m以上。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]