[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903928":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903928,584,2,"多选题","下列关于透层和黏层的施工说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在铺筑沥青层前1～2天，一次均匀洒布透层",false,{"key":16,"text":17,"correct":18},"B","采用乳化沥青作透层时，洒布后应尽早铺筑面层",true,{"key":20,"text":21,"correct":14},"C","黏层宜在当天洒布完成，喷洒后严禁车辆行人通过",{"key":23,"text":24,"correct":14},"D","黏层油的品种和规格应根据下卧层的类型通过试洒确定",{"key":26,"text":27,"correct":18},"E","喷洒表面应保持干燥，当气温低于5℃或路面潮湿时严禁喷洒","BE","A项，透层施工采用沥青洒布车，在铺筑沥青层前1～2天，一次均匀洒布透层。B项，透层沥青洒布后应尽早铺筑面层。当采用乳化沥青作透层时，洒布后应待其充分渗透、水分蒸发后，方可铺筑沥青面层，时间不宜少于24h。C项，黏层宜在当天洒布完成，等乳化沥青破乳、水分蒸发完后才能铺筑上层沥青混凝土，喷洒后严禁车辆行人通过。D项，黏层油的品种和规格，应根据下卧层的类型通过试洒确定。E项，喷洒表面清扫干净，并保持干燥。当气温低于10℃或路面潮湿时严禁喷洒。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]