[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903926":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903926,584,2,"多选题","下列关于抗滑桩施工的相关说法符合规定的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","抗滑桩应分节开挖，挖一节立即支护一节",true,{"key":16,"text":17,"correct":14},"B","抗滑桩的开挖应在上一节护壁混凝土终凝后进行",{"key":19,"text":20,"correct":21},"C","抗滑桩的开挖桩群应从两端沿滑坡主轴连续开挖",false,{"key":23,"text":24,"correct":14},"D","桩身混凝土的灌注必须连续进行",{"key":26,"text":27,"correct":14},"E","桩板式抗滑挡墙压实墙背填土时不得直接碾压锚索","ABDE","ABC三项，抗滑桩的开挖及支护规定包括：应分节开挖，每节高度宜为0.6～2m，挖一节立即支护一节；护壁应经过设计计算确定，护壁混凝土应紧贴围岩灌注，灌注前应清除孔壁，护壁宜设泄水孔；开挖应在上一节护壁混凝土终凝后进行，模板的支撑应在混凝土强度达到能保持护壁结构不变形后方可拆除；应在护壁内顺滑动方向用临时横撑加强支护；开挖桩群应从两端沿滑坡主轴间隔开挖，桩身强度不低于75%时可开挖邻桩。D项，灌注桩身混凝土前，应检查断面净空、清洗混凝土护壁，灌注必须连续进行。E项，对于桩板式抗滑挡墙，桩身混凝土应达到设计强度后方可安装挡土板，边安装边回填，并做好板后排水设施；应严格控制墙背填土的压实度，压实时不得直接碾压锚索（杆）。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]