[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903923,584,2,"多选题","对现有地基的陷穴、暗穴，不可以采用（ ）等措施。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","灌砂",false,{"key":16,"text":17,"correct":14},"B","灌浆",{"key":19,"text":20,"correct":21},"C","拦截",true,{"key":23,"text":24,"correct":14},"D","开挖回填",{"key":26,"text":27,"correct":21},"E","重锤压实","CE","路基范围内的陷穴，应在其发源地点对陷穴进口进行封填，并截排周围地表水。现有的陷穴、暗穴，可采用灌砂、灌浆、开挖回填、导洞和竖井等措施进行填充。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]