[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903919":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903919,584,2,"多选题","下列关于填石渗沟的说法符合施工规定的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","渗水材料的顶面（指封闭层以下）不得低于原地下水位",true,{"key":16,"text":17,"correct":18},"B","砂宜采用粉砂、细砂，含泥量应小于2%",false,{"key":20,"text":21,"correct":14},"C","用于排除层间水时，渗沟底部应埋置在最下面的不透水层",{"key":23,"text":24,"correct":14},"D","在冰冻地区，渗沟埋置深度不得小于当地最小冻结深度",{"key":26,"text":27,"correct":14},"E","填石渗沟纵坡不宜小于1%","ACDE","砂宜采用中砂，含泥量应小于2%，严禁用粉砂，细砂。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]