[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903914":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903914,584,2,"多选题","土质路堑的施工要求说法正确的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","应根据地面坡度、开挖断面、纵向长度及出土方向等因素，结合土方调配，选用安全、经济的开挖方案",true,{"key":16,"text":17,"correct":14},"B","应采取临时排水措施，确保施工作业面不积水。施工遇到地下水时应采取排导措施，将水引入路基排水系统；路床土含水率高或为含水层时，应采取设置渗沟、换填、改良土质、土工织物等处理措施，路床填料应具有良好的透水性能",{"key":19,"text":20,"correct":14},"C","可作为路基填料的土方，应分类开挖分类使用",{"key":22,"text":23,"correct":14},"D","土方开挖应自上而下进行，不得乱挖超挖，严禁掏底开挖",{"key":25,"text":26,"correct":27},"E","开挖至零填、路堑路床部分后，应尽快进行路床施工；如不能及时施工宜在设计路床顶高程以上预留至少500mm厚的保护层",false,"ABCD","本题考查的是路基施工工程。选项E错误，开挖至零填、路暂路床部分后，应尽快进行路床施工；如不能及时施工宜在设计路床顶高程以上预留至少300mm厚的保护层。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]