[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903906":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903906,584,2,"多选题","关于热拌沥青混合料路面摊铺说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各层开工前28天在监理工程师批准的现场备齐全部机械设备进行试验段铺筑",false,{"key":16,"text":17,"correct":18},"B","底、中、面层采用走线法施工，表面层采用平衡梁法施工",true,{"key":20,"text":21,"correct":14},"C","在摊铺过程中不准随意变换速度但可以中途停顿",{"key":23,"text":24,"correct":18},"D","开铺前将摊铺机的熨平板进行加热至不低于65℃",{"key":26,"text":27,"correct":18},"E","摊铺机无法作业的地方，在监理工程师同意后采取人工摊铺施工","BDE","本题考查的是路面工程。选项A错误，试验段开工前28天安装好试验仪器和设备，配备好的试验人员报请监理工程师审核。各层开工前14天在监理工程师批准的现场备齐全部机械设备进行试验段铺筑，以确定松铺系数、施工工艺，机械配备、人员组织、压实遍数，并检查压实度、沥青含量、矿料级配、沥青混合料马歇尔各项技术指标等；选项C错误，摊铺机均匀行驶，行走速度和拌和站产量相匹配。在摊铺过程中不准随意变换速度或中途停顿。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]