[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903902":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903902,584,2,"多选题","编制施工组织设计时，要充分考虑施工生产过程中（ ）的相互关系。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","连续性",true,{"key":16,"text":17,"correct":18},"B","专用性",false,{"key":20,"text":21,"correct":14},"C","平行性",{"key":23,"text":24,"correct":14},"D","协调性",{"key":26,"text":27,"correct":14},"E","均衡性","ACDE","公路工程施工组织设计是指对拟建工程项目提出科学的实施计划，从工程项目实际出发，确定合理的施工组织及施工方案，科学安排施工进度计划、施工平面、施工现场的规划，并作为编制工程造价和指导施工的依据。编制施工组织设计时，要充分考虑施工生产过程中的连续性、平行性、协调性和均衡性的相互关系，它是公路工程施工作业的基本组合方式，是作为计算分析和合理配置各种资源的重要依据。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]