[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903897":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903897,584,2,"多选题","公路施工组织设计中的资源组织计划包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","劳动力配置计划",true,{"key":16,"text":17,"correct":18},"B","辅助材料计划",false,{"key":20,"text":21,"correct":14},"C","主要施工机具、设备计划",{"key":23,"text":24,"correct":18},"D","永久工程计划",{"key":26,"text":27,"correct":14},"E","技术组织措施计划","ACE","公路施工组织设计中，资源组织计划包括：①劳动力配置计划。②主要材料计划。③主要施工机具、设备计划。④临时工程计划。⑤技术组织措施计划。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]