[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903891":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903891,584,2,"多选题","根据公路工程施工组织设计阶段的不同，施工组织设计可以划分为两类：一类是投标前编制的施工组织设计（简称“ 标前设计” ），另一类是签订工程承包合同后编制的施工组织设计（简称“ 标后设计” ）。两类施工组织设计的区别说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","标前设计是由项目管理层编制的",false,{"key":16,"text":17,"correct":18},"B","标后设计是由项目管理层编制的",true,{"key":20,"text":21,"correct":18},"C","标前设计具有规划性",{"key":23,"text":24,"correct":14},"D","标后设计具有规划性",{"key":26,"text":27,"correct":18},"E","标后设计服务周期从施工准备至验收","BCE","本题考查的是公路工程施工组织设计。 两类施工组织设计的区别 表5.1.1",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]