[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903716":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},903716,584,2,"多选题","预应力连续梁桥施工方法包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","顶推法",true,{"key":16,"text":17,"correct":14},"B","悬臂法",{"key":19,"text":20,"correct":14},"C","预制吊装",{"key":22,"text":23,"correct":24},"D","跨墩门架安装",false,{"key":26,"text":27,"correct":14},"E","支架现浇","ABCE","本题考查的是桥梁上部构造。预应力连续梁跨越能力大，常用的施工方法有顶推法、悬臂法、预制吊装（先简支后连续）及支架现浇等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]