[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903595,584,1,"单选题","公路基本建设项目一般采用（ ）设计。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一阶段",false,{"key":16,"text":17,"correct":18},"B","两阶段",true,{"key":20,"text":21,"correct":14},"C","三阶段",{"key":23,"text":24,"correct":14},"D","四阶段","公路基本建设项目一般采用两阶段设计。对于技术简单、方案明确的小型项目，可采用一阶段设计。对于技术复杂、基础资料缺乏或不足的建设项目，或建设项目中的特殊大型桥梁、隧道、互通式立体交叉等部分工程，必要时可采用三阶段设计。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]