[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903582,584,1,"单选题","采用两阶段设计的建设项目，初步设计文件一经主管部门批准，（ ）是建设项目投资的最高限额，不得随意突破。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算",false,{"key":16,"text":17,"correct":18},"B","工程概算",true,{"key":20,"text":21,"correct":14},"C","修正概算",{"key":23,"text":24,"correct":14},"D","施工图预算","本题考查的是公路工程设计。初步设计文件一经主管部门批准，其概算就是建设项目投资的最高限额，不得随意突破。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]