[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903564,584,1,"单选题","工程量清单计价属于项目实施阶段的造价文件编制，其组成不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招（投）标工程量清单",false,{"key":16,"text":17,"correct":18},"B","工程设计费用文件",true,{"key":20,"text":21,"correct":14},"C","合同工程量清单",{"key":23,"text":24,"correct":14},"D","计量与支付文件","根据《公路工程建设项目造价文件管理导则》的规定（JTG 3810—2017），工程量清单计价属于项目实施阶段的造价文件编制，其组成如下：①招（投）标工程量清单；②工程量清单预算；③合同工程量清单；④计量与支付文件；⑤工程变更费用文件；⑥造价管理台账。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]