[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},903560,584,1,"单选题","工程量清单计价与定额计价的差异不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程量清单计价与定额计价的主要计价依据不同",false,{"key":16,"text":17,"correct":14},"B","工程量清单计价与定额计价的表现形式不同",{"key":19,"text":20,"correct":21},"C","定额计价是以工程量清单为表现形式",true,{"key":23,"text":24,"correct":14},"D","工程量清单计价中单价与定额计价中的技术经济指标的内涵不同","定额计价是以费用项目清单为表现形式，以定额为主要依据，计算确定工程造价和技术经济指标的方式。工程量清单计价与定额计价的差异具体包括以下几个方面：①工程量清单计价与定额计价的主要计价依据不同，因此所反映的消耗量水平也可能不同；②工程量清单计价与定额计价的表现形式不同；③工程量清单计价中单价与定额计价中的技术经济指标的内涵不同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]