[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903554,584,1,"单选题","下列对工程量清单计量规则的作用描述错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定了清单子目所包含的工作内容",false,{"key":16,"text":17,"correct":18},"B","工程量清单计量规则是设计工程量的理论依据",true,{"key":20,"text":21,"correct":14},"C","对承包人完成子目工作的工艺流程、施工过程提出了具体的要求",{"key":23,"text":24,"correct":14},"D","对承包人完成子目工作的工程质量提出了对应的质量检验标准","工程量清单计量规则的作用主要包括：①工程量清单计量规则是计量工程量的计算依据；②工程量清单计量规则确定了清单子目所包含的工作内容；③工程量清单计量规则对承包人完成子目工作的工艺流程、施工过程提出了具体的要求；④工程量清单计量规则、技术规范对承包人完成子目工作的工程质量提出了对应的质量检验标准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]