[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903545":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},903545,584,1,"单选题","报价时招标文件各部分的优先次序说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同专用条款及数据表优先于合同通用条款",true,{"key":16,"text":17,"correct":18},"B","图纸中的工程数量优先于工程量清单中的工程数量",false,{"key":20,"text":21,"correct":18},"C","工程量清单中项目划分、计量与技术规范须独立考虑",{"key":23,"text":24,"correct":18},"D","合同通用条款及数据表优先于合同专用条款","本题考查的是工程量清单计量规则。报价时招标文件各部分的优先次序应是：合同专用条款及数据表（含招标文件补遗书中与此有关部分）优先于合同通用条款；工程量清单中的工程数量（含招标文件补遗书中与此有关的部分）优先于图纸中的工程数量；工程量清单中项目划分、计量与技术规范必须相结合。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]