[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},903543,584,1,"单选题","工程量的计算需要按照一定的工程量计算规则逐项进行，定额工程量计算的主要依据不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经审定通过经济调查资料",false,{"key":16,"text":17,"correct":14},"B","经审定的施工组织设计",{"key":19,"text":20,"correct":21},"C","未经审定的设计图纸",true,{"key":23,"text":24,"correct":14},"D","国家、行业发布的各类消耗量定额","定额工程量计算的主要依据包括：①国家、行业和地方发布的各类消耗量定额及其对应工程最计算规则。②经审定的设计图纸及说明。③经审定的施工组织设计或施工技术方案。④经审定通过的其他有关技术经济文件及经济调查资料。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]