[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903540,584,1,"单选题","在公路工程实施阶段，对已完工程进行计量后，按合同约定确认进行支付的计量工程量是指（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","清单工程量",false,{"key":16,"text":17,"correct":14},"B","合同工程量",{"key":19,"text":20,"correct":14},"C","计量工程量",{"key":22,"text":23,"correct":24},"D","支付工程量",true,"支付工程量是在公路工程实施阶段，对已完工程进行计量后，按合同约定确认进行支付的计量工程量。支付工程量对应工程实施阶段项目对已完工程数量进行确定支付这一环节，支付工程量之和与计量工程量之和在竣工结算时应是相同的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]