[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},903539,584,1,"单选题","招标人编制工程量清单时，依据施工图纸、招标文件、技术规范确定的工程数量称之为（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","清单工程量",true,{"key":16,"text":17,"correct":18},"B","合同工程量",false,{"key":20,"text":21,"correct":18},"C","计量工程量",{"key":23,"text":24,"correct":18},"D","支付工程量","本题考查的是公路工程定额工程量计算规则。清单工程量是招标人编制工程量清单时，依据施工图纸、招标文件、技术规范确定的工程数量。清单工程量一般是投标人投标报价的基准数量，是签订合同的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]