[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903538,584,1,"单选题","除了涉及实体工程数量的计算外，还需计算为修建实体而必须消耗的辅助工程的工程数量的量为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","清单工程量",false,{"key":16,"text":17,"correct":18},"B","定额工程量",true,{"key":20,"text":21,"correct":14},"C","计量工程量",{"key":23,"text":24,"correct":14},"D","支付工程量","本题考查的是公路工程定额工程量计算规则。清单工程量的计算范围通常为工程的实体，而定额工程量除了涉及实体工程数量的计算外，还需计算为修建实体而必须消耗的辅助工程的工程数量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]