[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},903537,584,1,"单选题","辅助工程的工程数量，主要依据不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","概、预算编制人员的工作经验",false,{"key":16,"text":17,"correct":14},"B","工程实际情况",{"key":19,"text":20,"correct":21},"C","定额规定的工程量",true,{"key":23,"text":24,"correct":14},"D","施工组织设计","辅助工程是指为了保证主体工程的形成和质量，施工中必须采取的措施或修建的一些临时工程。这部分工程一般在施工完成后，也随之拆除或消失。辅助工程的工程数量，主要依靠概、预算编制人员的工作经验、施工组织设计及工程实际情况来确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]