[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903531,584,1,"单选题","在编制概、预算时，需要考虑的辅助工程工程量不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","清除表土或零填地段的基底压实、耕地填前碾压的回填数量",false,{"key":16,"text":17,"correct":18},"B","路基、路面、桥梁、涵洞以及隧道工程",true,{"key":20,"text":21,"correct":14},"C","为保证路基边缘压实而加宽填筑的数量",{"key":23,"text":24,"correct":14},"D","临时工程","在编制概、预算时，需要考虑的辅助工程工程量主要包括：①构造物的挖基、排水；②清除表土或零填地段的基底压实、耕地填前碾压的回填数量；③因路基沉陷增加的数量；④为保证路基边缘压实而加宽填筑的数量；⑤临时工程（汽车便道，便桥，轨道铺设，临时电力、电信设施等）；⑥桥梁工程中的围堰、护筒、工作平台、吊装设备、混凝土构件运输、预制厂及设施（底座、张拉台座等）、拌和站、蒸汽养护设施等。B项，路基、路面、桥梁、涵洞以及隧道工程属于主体工程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]