[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903528,584,1,"单选题","定额或指标的计量单位主要是根据单位分部分项工程和（ ）确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","结构构件的受力特性",false,{"key":16,"text":17,"correct":18},"B","结构构件的形体特征及其变化",true,{"key":20,"text":21,"correct":14},"C","结构构件的费用",{"key":23,"text":24,"correct":14},"D","结构构件的消耗量","定额或指标的计量单位主要是根据单位分部分项工程和结构构件的形体特征及其变化确定。由于工作内容综合，计量单位亦具有综合的性质。工程量计算规则的规定应确切反映项目所包含的工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]