[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},903514,584,1,"单选题","下列费用不能计入雨季施工增加费的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因雨季施工所需增加的工、料、机费用的支出",false,{"key":16,"text":17,"correct":14},"B","材料因雨季受潮、受湿的耗损费用",{"key":19,"text":20,"correct":21},"C","因50年一遇的大暴雨，防止雨水必须采取的防护措施的费用",true,{"key":23,"text":24,"correct":14},"D","路基土方工程的开挖和运输，因雨季施工引起的黏附工具、降低工效所增加的费用","本题考查的是公路工程造价费用组成。雨季施工增加费的内容包括：（1）因雨季施工所需增加的工、料、机费用的支出，包括工作效率的降低及易被雨水冲毁的工程所増加的工作内容等。（2）路基土方工程的开挖和运输，因雨季施工（非土壤中水影响）而引起的黏附工具、降低工效所增加的费用。（3）因防止雨水必须采取的防护措施的费用。（4）材料因受潮、受湿的耗损费用。（5）增加防雨、防潮设备的费用。（6）其他有关雨季施工所需增加的费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]