[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903416,584,1,"单选题","下列关于变压器、箱式变电所安装要求说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","变压器的交接试验应符合相关规定",false,{"key":16,"text":17,"correct":14},"B","1000kVA以上变压器应做器身检查",{"key":19,"text":20,"correct":14},"C","变压器的低压侧中性点直接与接地干线连接",{"key":22,"text":23,"correct":24},"D","油浸变压器运至现场2个月内不能安装时应检查油箱密封情况",true,"变压器、箱式变电所的安装要求包括：①变压器的低压侧中性点、箱式变电所的N母线和PE母线直接与接地装置的接地干线连接，变压器箱体、干式变压器的支架或外壳应接地线（PE）。②油浸变压器运到现场后，如3个月内不能安装时，应检查油箱密封情况，做油的绝缘测试，并注以合格油。③除厂家有规定外，1000kVA以上变压器应做器身检查。④变压器的交接试验应符合相关规定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]