[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903414,584,1,"单选题","下列关于光缆接头要求说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","套管内装防潮剂和接头责任卡",false,{"key":16,"text":17,"correct":18},"B","若采用热可缩套管，热缩完毕后即可搬动",true,{"key":20,"text":21,"correct":14},"C","封装完毕后测试检查接头损耗并做记录",{"key":23,"text":24,"correct":14},"D","“O”形圈的曲率半径不小于光缆直径的20倍","光缆接头套管的封装，应符合下列要求：接头套管的封装按工艺要求进行，套管内装防潮剂和接头责任卡。若采用热可缩套管，加热应均匀，热缩完毕原地冷却后才能搬动，热缩后外形美观，无烧焦等不良状况。封装完毕，测试检查接头损耗并做记录。管道光缆接头安装在入孔正方的光缆接头盒托架上接头余缆紧贴入孔壁或入孔搁架，盘成“O”形圈，并用扎线固定。“O”形圈的曲率半径不小于光缆直径的20倍。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]