[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903384,584,1,"单选题","下列关于悬索桥索塔施工说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","大跨度悬索桥国内主要采用钢筋混凝土塔",false,{"key":16,"text":17,"correct":14},"B","安装索鞍必须满足高空吊装重物的安全要求",{"key":19,"text":20,"correct":14},"C","索塔完工后，须测定桥塔倾斜度和塔顶高程",{"key":22,"text":23,"correct":24},"D","塔顶钢框架必须在索塔上系梁施工前完成安装",true,"A项，大跨度悬索桥塔身国内主要采用钢筋混凝土塔，国外主要采用钢塔。B项，安装索鞍时必须满足高空吊装重物的安全要求，一般选择在白天晴朗时连续完成工作。C项，索塔完工后，须测定桥塔倾斜度、跨距和塔顶高程，作为主缆线形计算调整的依据。D项，塔顶钢框架的安装必须在索塔上系梁施工完毕后方能进行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]