[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903337,584,1,"单选题","预应力钢筋张拉锚固后，孔道应尽早压浆，且应在（ ）h内完成",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":14},"C","28",{"key":22,"text":23,"correct":24},"D","48",true,"本题考查的是桥涵工程施工技术。预应力钢筋张拉锚固后，孔道应尽早压浆，且应在48h内完成，否则应采取防止预应力钢筋锈蚀的措施。压浆完成后，需要封锚的锚具，应对梁端混凝土凿毛并将其周围冲洗干净，设置钢筋网浇筑封锚混凝土，封锚采用与构件同强度的混凝土并严格控制封锚后梁体长度。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]