[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903324":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903324,584,1,"单选题","对设计为漂浮或半漂浮体系的斜拉桥，在主梁施工期间应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","保持设计状态",false,{"key":16,"text":17,"correct":18},"B","使塔梁临时固结",true,{"key":20,"text":21,"correct":14},"C","使塔梁永久固结",{"key":23,"text":24,"correct":14},"D","使塔梁处于自由状态","本题考查的是桥涵工程施工技术。斜拉桥主梁应严格按照预定的程序、方法和措施进行施工。对设计为漂浮或半漂浮体系的斜拉桥，在主梁施工期间应使塔梁临时固结。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]