[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903298,584,1,"单选题","先开挖隧道两侧的导坑，并进行初期支护，再分部开挖剩余部分，一般适用于浅埋大跨度隧道及地表下沉量要求严格而围岩条件很差的情况的隧道施工方法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","台阶法",false,{"key":16,"text":17,"correct":14},"B","环形开挖预留核心土法",{"key":19,"text":20,"correct":14},"C","中隔壁法（CD法）",{"key":22,"text":23,"correct":24},"D","双侧壁导坑法",true,"本题考查的是公路隧道施工技术。双侧壁导坑法：先开挖隧道两侧的导坑，并进行初期支护，再分部开挖剩余部分的施工方法。一般适用于浅埋大跨度隧道及地表下沉量要求严格而围岩条件很差的情况。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]